The contract is for the direct purchase of materials for the McCarty Ranch Potable Water Main Extension project. The initial contract amount was $362,644.77, but an amendment increased the amount by $25,491.04 to $388,135.81. The contract duration is from September 19, 2024, to October 31, 2025. The contractor is Ferguson Enterprises, LLC dba Ferguson Waterworks. The project involves the purchase of various water main materials, including pipes, valves, and fittings.
• The contract is for a specific project, the McCarty Ranch Potable Water Main Extension.
• The initial contract amount was $362,644.77.
• An amendment increased the contract amount by $25,491.04.
• The contract duration is approximately 1 year.
• The contractor is Ferguson Enterprises, LLC dba Ferguson Waterworks.
• The project involves the purchase of water main materials.