This contract is for the exterior perimeter security improvements at Topeka West High School. The project includes the installation of a translucent canopy, limestone boulders, a concrete ADA ramp, and other security features. The contract was awarded to Construction, Inc. for a total of $460,455.00. The project is expected to be completed in 145 calendar days.
• The contract includes a base bid and several alternates, including the installation of a translucent canopy and a concrete ADA ramp.
• The project is expected to be completed in 145 calendar days.
• The contract was awarded to Construction, Inc. for a total of $460,455.00.
• The project includes the installation of limestone boulders and other security features.
• The contract includes a unit price for the removal of unsatisfactory soil and replacement with satisfactory soil material.
• The contract includes a unit price for rock excavation and replacement with satisfactory soil material.