This contract is a municipal street‑resurfacing project for the City of Worcester, covering nine city streets and associated sidewalks, curbs, drainage, and utility work. The scope includes pulvi‑milling, full‑depth grinding, overlay work, replacement of curbs and gutters, installation of new asphalt binder courses, concrete sidewalk repair, and limited water‑main work on two segments. A $190,000 lump‑sum reserve is included for unforeseen items, and the contract is awarded on a unit‑price basis with a total bid price of just over $2 million.
• Streets: Brattle, Chester, Hastings, Nottingham, Orlando, Otsego, Park, Sagamore, Smith (total ≈ 7,300 ft).
• Key tasks: milling, grinding, Superpave asphalt placement, curb & gutter work, sidewalk concrete repair, utility box relocation, and water‑main repairs on Hastings Ave. and Nottingham Rd.
• Schedule: Bids due 1 Apr 2022; work must begin by 15 Oct 2022, be winter‑stabilized by 18 Nov 2022, and fully completed by 15 Nov 2022 with liquidated damages of $250/day for late completion.