The City of Palm Bay, Florida, issued a solicitation for the renovation of the Palm Bay Aquatic Center. The project involves providing labor, materials, management, and coordination for the renovation, including the installation of a PVC liner, swimming pool sealants, and caulking. The project also includes mechanical room add alternates, deck add alternates, and aesthetics add alternates. The solicitation was rejected on February 12, 2020.
• The project requires the contractor to provide all necessary equipment and services for the renovation.
• The contractor must obtain final acceptance by the jurisdictional health department(s).
• The contractor must provide initial pool water fill and initial chemical balancing.
• The contractor must coordinate for all required bonding and grounding of the pool shell, fittings, and equipment.
• The contractor must provide the main drain hydrostatic relief system as shown on the drawings.