The contract is for the Early Site Development phase of construction for the North County Community Office. The project includes preparatory site work, frontage improvements, and on-site underground improvements. The engineer's estimate for the project is $3,400,000.00. The contract was awarded to Trimaxx Construction, Inc.
• The project location is at 17601 59th Ave. NE, in the City of Arlington, in Snohomish County, Washington.
• The project includes expansion of 59th, curb and gutter, and a pedestrian sidewalk.
• The project also includes installation of asphalt treated base and on-site underground improvements, including storm, sewer, water, communication, electrical.
• Bidders were required to attend one mandatory teleconference pre-bid meeting.
• The bid opening was held on March 30, 2021, at 2:00 p.m.