The City of Spokane issued RFP 6187‑24 for the as‑needed reconditioning of electric motors used in its solid‑waste‑to‑energy operations. After receiving two proposals, the City evaluated technical, management, and cost criteria, ultimately recommending K&N Electric Motors, Inc. as the awardee pending City Council approval. The contract is structured as an indefinite‑delivery vehicle covering a five‑year period, with an estimated annual spend of roughly $100 K (approximately $500 K total).
• Scope: off‑site motor reconditioning on an as‑needed basis for waste‑to‑energy facilities.
• Evaluation: weighted scoring (40 % technical, 30 % management, 40 % cost) led to K&N’s selection.
• Timeline: bids due 9/30/2024; award intent 10/17/2024; formal award 12/9/2024; performance Jan 1 2025–Dec 31 2029.
• Funding: engineered estimate $100 K per year, no explicit dollar ceiling disclosed.