The Port Authority of Allen County is seeking sealed proposals to relocate or remove an excess soil stockpile behind the Jay Begg Parkway property in Allen County, Ohio. The project involves moving approximately 119,000 cubic yards of soil (the total stockpile is ~136,000 CY, with 17,000 CY retained on‑site). Contractors must provide cost, schedule, haul‑route, traffic‑management, erosion‑control, and coordination plans, and must complete the work within a 45‑day window after mobilization, with final completion no later than December 31 2026.
• Scope: Excavation and haul of ~119,000 CY of soil, plus seeding/mulching (52,133 SY), erosion‑control fence (4,171 LF), and construction layout stakes (lump).
• Schedule: Mobilization ≤ 2 weeks after award; execution ≤ 45 working days; project must finish by 12/31/2026.
• Requirements: Unit‑price bids only (no lump‑sum), performance and bid bonds, tax‑exempt status, prevailing‑wage compliance, environmental/erosion controls, and a coordination plan with PAAC and Randall Bearings.