The Houston County School District is seeking proposals for repaving the athletic track at Mossy Creek Middle School. The project involves removing debris, laser grading, compacting stone base, installing asphalt binder and surface courses, and striping the track according to NFHS rules and regulations. The contractor will also be responsible for installing a high jump pad and long jump runway and pit. A mandatory site visit is scheduled for October 14, 2025, at 08:30 AM.
• The project requires the removal of debris and laser grading of the stone base to a minimum of 95% relative compaction.
• The contractor must install 1.5” asphalt binder course and 1.5” type II asphalt surface course, compacted to at least 93% of the Maximum Theoretical Laboratory Specific Gravity.
• The track must be striped according to NFHS rules and regulations.
• A high jump pad and long jump runway and pit must be installed, meeting NFHS standard sizes, dimensions, and regulations.
• The contractor is responsible for ensuring the finished product meets NFHS tolerances on slopes and finishes.