The City of Salina is soliciting sealed‑bid contractors to perform concrete sidewalk, curb‑and‑gutter, and pavement work for several city parks (Phase 4B). The base scope includes excavation, concrete placement, aggregate base, seeding/grass planting, traffic‑control planning, and site‑staking. Four optional alternates (Kenwood Park, medians, Bill Burke Park, Sunset Park) may be awarded in addition to the base work. The contract is a fixed‑price, performance‑bonded construction award with a substantial‑completion deadline of 03 Jan 2027 and final completion by 01 Apr 2027.
• Primary work: new concrete sidewalks (4‑in, 5‑in, 6‑in), curb‑and‑gutter, reinforced concrete pavement, aggregate base, and landscaping seeding.
• Quantity: roughly 2,400 sq yd of concrete work, 328 cy of excavation, and extensive site‑prep and traffic‑control measures.
• Mandatory deliverables: performance and statutory payment bonds, insurance coverage, $36 filing fee, and 5 % bid security.
• Schedule: bids due 2 p.m. CST May 21 2026; substantial completion Jan 3 2027; final completion Apr 1 2027.
• Evaluation: lowest responsive and responsible bidder; liquidated damages $300/day for late completion.