The project involves the removal and replacement of existing asphalt pavement, concrete curb, and sidewalks, as well as the installation of new fencing, lighting, and erosion control measures at Lincoln School in Kent County, Michigan. The project is expected to be completed in three phases, with substantial completion by August 7, 2026, and final completion by October 2, 2026. The contractor will be responsible for coordinating with the school district staff and utilities to ensure a smooth construction process.
• The project includes the removal of 7,000 SY of existing asphalt pavement and replacement with 7,000 SY of new asphalt pavement.
• The contractor will also install new concrete curb and sidewalks, fencing, lighting, and erosion control measures.
• The project requires the contractor to obtain necessary permits and approvals from the school district and other regulatory agencies.
• The contractor will be required to provide a bid bond, certified check, or cashier's check payable to the Kent Intermediate School District in an amount equal to 5% of the total price.
• The project will be awarded to the lowest responsible bidder, and the contract will be executed within 15 days after the award.