The Illinois Toll Highway Authority is giving notice of intent to amend its contract with F.H. Paschen, S.N. Nielsen to provide for Stage 6 and 7 Schedule Recovery for work related to I-294 Roadway Reconstruction/Widening. The original contract award amount was $104,068,807.95, and the cost of the extra work order/change order is $2,600,000.00. The work includes construction services, general, including maintenance and repair services.
• The project involves I-294 Roadway Reconstruction/Widening.
• The original contract award amount was $104,068,807.95.
• The cost of the extra work order/change order is $2,600,000.00.
• The contractor is F.H. Paschen, S.N. Nielsen.
• The project requires construction services, general, including maintenance and repair services.