The City of Laguna Beach is seeking a qualified contractor to repair and strengthen post‑tensioned beams, replace anchor bolts, perform concrete spall repairs, install waterproofing grout, and apply a polyurethane traffic‑coating system, as well as replace wheel stops and restripe the top‑floor parking stalls of the Glenneyre Street Parking Structure. The work includes traffic control, phasing, and compliance with extensive safety, environmental, and prevailing‑wage requirements, and must be completed within a 65‑working‑day schedule while observing strict parking‑space closure limits and a seasonal work stoppage.
• Structural repairs: post‑tensioned beam reinforcement, steel thru‑bolts, side brackets, and anchor bolt installations with pull‑test verification.
• Concrete and waterproofing: spall repair, epoxy injection, and injection grouting of drainage lines.
• Surface treatment: Sikalastic 720 polyurethane traffic coating, wheel‑stop replacement, and complete restriping of top‑floor stalls.
• Project constraints: only one floor closed at a time, max 50 parking spaces closed, mandatory pre‑bid conference, 5‑day top‑floor coating window, no work May 31 – Sept 6 2027, and $1,500 per day liquidated damages for overruns.