The Colonial School District is soliciting bids for two re‑bid contracts under Bid Package B for the John G. Leach School renovation. Contract B‑14 covers casework and millwork (carpentry, cabinetry, and related wood‑shop work) while Contract B‑26 covers all electrical systems (wiring, power distribution, lighting, etc.). The work must comply with Delaware’s Architectural Accessibility Act, prevailing‑wage requirements (rates effective 14 Mar 2025), mandatory drug‑testing (OMB 4104), craft‑training (if ≥10 workers), and the Contractor Registration Act (effective 1 Jul 2021). Bids must be secured with a 10 % bid security plus a surety consent and submitted by 3:30 PM on 28 Jan 2026 at Gunning Bedford Middle School, New Castle, DE. A pre‑bid meeting is scheduled for 7 Jan 2026 (optional). All required documents are available online after 30 Dec 2025, and detailed drawings can be requested via a plan‑request form (two‑week access window).
• Two contracts: B‑14 (casework & millwork) and B‑26 (electrical)
• Location: John G. Leach School, New Castle County, DE
• Bid security: 10 % of total bid plus surety consent
• Mandatory compliance: Accessibility Act, prevailing‑wage schedule, OMB 4104 drug‑testing, craft‑training, Contractor Registration Act
• Pre‑bid meeting: 7 Jan 2026 (optional)
• Bid deadline: 28 Jan 2026, 3:30 PM (sealed bids)
• Documents online after 30 Dec 2025; drawings request via
[email protected]
• Primary contact for questions: Jason Hartman, (302) 593‑5230,
[email protected]