The U.S. Army Corps of Engineers is soliciting a total‑small‑business set‑aside for the design and construction of a pre‑engineered metal storage canopy (Phase III) at the Carrollton flood‑wall site in New Orleans, LA. The contract includes demolition, clearing, excavation, utility relocations, concrete slab and pavement work, erection of a reinforced‑concrete foundation, installation of a pre‑engineered metal building, chain‑link fencing, gates, and associated incidental work. The scope is detailed in 13 drawings and specifications and must comply with UFC 3‑301‑01, ASCE 7‑22, and relevant wind, seismic, and fire design criteria. The period of performance is 150 calendar days from notice to proceed, with a total contract value estimated between $1 M and $5 M.
• Demolition, clearing, grubbing, and site preparation
• Structural excavation, backfill, and utility relocations
• Construction of reinforced concrete slab and pavement
• Erection of a pre‑engineered metal storage building (PEMB) per specified wind, seismic, and fire standards
• Installation of chain‑link fencing, gates, and related hardware
• Compliance with detailed drawings (G‑003, C‑101, S‑200) and specifications (including skylights, corrosion protection, and warranty requirements)
• Small‑business set‑aside; NAICS 237990 (Other Heavy and Civil Engineering Construction)
• Bid deadline: 23 Sep 2026, 10:00 AM; period of performance: 150 days