The Illinois Toll Highway Authority is giving its notice of intent to amend its contract with Lorig Construction Company to provide for Extended Maintenance of Traffic for work related to I-294 Roadway and Bridge Reconstruction and Widening. The original contract award amount was $130,421,625.65 and the cost of the change order/extra work order is $188,141.01. The work includes construction services, general, including maintenance and repair services.
• The contract is for the I-294 Roadway and Bridge Reconstruction and Widening project.
• The original contract award amount was $130,421,625.65.
• The cost of the change order/extra work order is $188,141.01.
• The work includes construction services, general, including maintenance and repair services.
• The contractor is Lorig Construction Company.