The City of Charlotte is soliciting bids for Phase II of its Perimeter Fence Upgrade at Charlotte Douglas International Airport. The contractor will replace roughly 21,000 linear feet of existing 6‑ft chain‑link fence along Runway 18R/36L with a 10‑ft high security fence, install anti‑burrow barriers, barbed‑wire/concertina, and upgrade several airfield gates and concrete pads. Work must comply with FAA Cert Alert 16‑03, the Airport Security Plan, and all applicable FAA, TSA, and CLT security requirements. The project is scheduled for award shortly after the March 5, 2026 bid opening, with a substantial‑completion window of 253 calendar days and final acceptance within an additional 30 days.