This project will widen the Ray Road and Dobson Road intersection, adding dual left‑turn lanes, bike lanes, a raised landscaped median, curb and gutter, sidewalks, ADA upgrades, traffic signal and interconnect upgrades, LED streetlights, storm‑drainage, irrigation, utility relocations, and right‑of‑way work. The scope includes extensive earthwork, concrete and asphalt paving, utility coordination (water, gas, electric, fiber‑optic), traffic control, landscaping, and a 700‑day construction schedule. The contract is federally funded with an engineer’s estimate between $14 M and $18 M, requiring a 10 % bid bond and 100 % performance/payments bonds, and strict compliance with federal, state, and city regulations.
• Roadway widening, new median, sidewalks, and ADA‑compliant upgrades
• Installation of new traffic signals, LED lighting, and extensive utility relocation (including SRP 12 kV conduit)
• Comprehensive landscaping (71 trees, shrubs, irrigation) and storm‑drainage improvements
• Mandatory pre‑bid conference on September 16, 2026; bids due October 15, 2026