The City of Fresno is rebidding a roadway‑improvement project on Shaw Avenue between Fruit Avenue and Palm Avenue. The scope includes milling the existing asphalt, applying a 0.34‑inch hot‑mix overlay, reconstructing ADA‑compliant curb ramps, adjusting utility manholes and valve covers, installing new signage, striping, and replacing traffic‑loop detectors. The contract is funded with federal STPL 5060 aid and a total construction allocation of $1,898,180. Bidders must hold a valid California Class “A” or “C‑12” contractor license, submit a 10 % bid deposit, and be prepared to furnish 100 % payment and performance bonds after award. The work must be completed within 60 working days of the Notice to Proceed, with liquidated damages of $1,500 per day for late completion.
• Pavement work: 0.3 ft milling, 0.34 ft HMA overlay over ~0.7 mi.
• ADA‑related improvements: curb‑ramp reconstruction, utility adjustments, new signage/striping.
• Mandatory compliance: federal FHWA requirements, Davis‑Bacon prevailing‑wage rates, California labor‑code statutes, and City of Fresno CMIS reporting.
• Procurement deadlines: pre‑bid conference (June 17, 2026, optional), bid submission (July 7, 2026 3 PM), bid deposit 10 % of net bid, post‑award 100 % payment & performance bonds.