The Temecula Valley Unified School District (TVUSD) is seeking a qualified design‑build entity to deliver a new two‑story, approximately 20‑classroom building on the Temecula Valley High School campus, together with associated site‑improvement work. The scope covers full architectural‑engineering design, DSA‑approved construction documents, a second‑story bridge to the existing science building, demolition of existing relocatable classrooms, new sand‑volleyball courts, artificial‑turf installation, utility upgrades, ADA compliance, and a solar photovoltaic system (rooftop and canopy). The contractor must provide a design‑build schedule, meet target‑value design and a guaranteed maximum price (GMP) not to exceed the district’s maximum allowable price, and satisfy extensive bonding, insurance, labor‑code, and California public‑works certifications (DIR registration, Iran Contracting Act, DBE). The project schedule includes a 135‑day design phase (330 days total with DSA review) and a construction phase of up to 435 days, targeting substantial completion by 24 June 2028.
• 2‑story, 20‑classroom building with a bridge to existing Building 600.
• Site work: demolition, new sand‑volleyball courts, artificial turf, utility & infrastructure upgrades, ADA improvements.
• Solar PV system (rooftop & canopy) to meet Title 24 + 10 % energy efficiency.
• Design‑build delivery, target‑value design, GMP budgeting, 4 % owner‑controlled contingency, $2,500/day liquidated‑damage penalties.
• Mandatory pre‑submission site walk (May 29 2026) and full compliance with DIR registration, DBE certification, and all California labor‑code requirements.