The University Facilities Management at Montana State University is seeking a qualified contractor to fully renovate Lab 132 (the Harrison Extruder Laboratory) on the Bozeman campus. The work includes selective demolition, hazardous‑material handling, mechanical, electrical, and plumbing upgrades, installation of new HVAC and de‑humidification equipment, new lab finishes (sheet‑vinyl flooring, FRP backsplashes, integrated base), fire‑protection and life‑safety compliance, temporary facilities, waste management, O&M manual preparation, and end‑user training. Bids must be submitted by 2 PM on 20 Nov 2025, with a 10 % bid bond for any bid ≥ $150 k and full‑value performance and labor‑material bonds required after award. Substantial completion is required by 20 Apr 2026, with liquidated damages of $250 per day for delays.
• Scope covers demolition, new mechanical (HVAC, VAV, de‑humidifier, filtration), plumbing (new sinks, floor drains), electrical (new panels, receptacles, power for lab equipment), interior finishes (sheet‑vinyl flooring, FRP walls, integrated base), and commissioning/training.
• Mandatory pre‑bid site walk‑through on 3 Nov 2025 (attendance strongly recommended).
• Bonding requirements: 10 % bid security, 100 % performance and labor‑material bonds for contracts ≥ $150 k.
• Project size indicated by bids ranging from ~$92 k to ~$142 k, suggesting a modest‑size laboratory remodel.