Union Concrete and Construction Corp. invites qualified M/WBE & SDVOB subcontractors, suppliers, and trucking firms to provide quotes for the following project:
Buffalo Bills Stadium Demolition - Subcontract: 3201 Spoil Pile Load, Haul, Fill Existing Stadium
Scope of Work
SPECIFICATION SECTION 31 20 00 Earth Moving
provide all loading, hauling and placement of 340,000 cy of shale material from stockpile at ECC South 4041 Southwestern Blvd, Orchard Park, NY to be placed in the existing Buffalo Bills Stadium (facility located east of Abbott Rd) footprint in conjunction with mass demolition scope of work
provide flag person(s) as necessary to direct any truck traffic at entrance gate to ECC Campus Road, Southwestern Blvd
provide rough grading to subgrade from imported soils stock pile at ECC over crushed concrete layer placed at the bottom of the Stadium bowl from elevation 718.00
Provide an ADD Alternate #7 to provide all loading, hauling and placement for legal disposal of the balance of the shale material from the stockpile at ECC South 4041 Southwestern Blvd, Orchard Park, NY. 350,000 cy (loose fill material) to a proposed alternate disposal site upon completion of the filling operations for Base Bid Work
Provide an ADD Alternate #8 to provide all restoration of the area of the existing shale pile and haul roads from the shale material stockpile removal at ECC South 4041 Southwestern Blvd, Orchard Park, NY upon completion of the removal of stockpile. Scope to include placement of 6” topsoil from stockpile on site, fine grading a seeding to establish a lawn area, including removal and disposal of all SWPP silt fencing and temporary chain link fencing as required.
Letting Date: December 5, 2025
Project plans and documents are available from Union Concrete upon request. Please contact Erika Mellick at
[email protected]
Proposals can be sent via email to
[email protected]
Service-Disabled Veteran-Owned Business (SDVOB)
SDVOB Goal: 6.00%
Minority / Women Business Enterprise contracting goals (MWBE)
MBE Goal: 15.00%
WBE Goal: 15.00%