The City of Fresno is soliciting bids for “Pave More Now – Package B‑2,” a $14.28 M pavement‑rehabilitation program covering ten discrete roadway locations throughout Fresno. The work includes full‑depth asphalt grinding and overlay, isolated area reconstruction, curb‑ramp and sidewalk repairs, replacement of striping, advance stop bars, traffic‑signal loops, and adjustments to water‑valve and manhole lids to match final pavement grades. Bidders must provide a 10 % bid deposit, 100 % payment and performance bonds, comply with prevailing‑wage and the City’s Community Workforce Agreement, and submit all construction‑management data through the City’s CMIS. The contract must be executed within 15 calendar days of award and the construction period is limited to 180 working days from the Notice to Proceed, with liquidated damages of $1,000 per day for overruns.
• Scope: asphalt grind & overlay, full‑depth reconstruction, curb‑ramp, sidewalk, gutter, striping, traffic‑signal loop replacement, utility adjustments across 10 sites.
• Budget: $14,282,000 construction allocation; bonds and 10 % bid deposit required.
• Schedule: Pre‑bid Zoom conference May 5 2026; bid deadline May 19 2026 3 PM; 180‑working‑day construction window; $1,000/day liquidated damages.
• Requirements: Class A or C‑12 CA contractor license, 100 % payment & performance bonds, CMIS usage, prevailing‑wage compliance, 5 % local‑preference certification (if applicable).