The City of Homestead is seeking a qualified contractor to completely rebuild and repair a Fairbanks‑Morse OP blower and its associated vertical drive assembly for a power‑plant engine (model 38TDD8‑1/8). The contractor must provide all labor, materials, tools, and equipment, follow the manufacturer’s technical manual, and adhere to ANSI, NFPA, OSHA, and Federal Equipment Directive standards. Work includes disassembly, inspection, machining, part replacement, cleaning, reassembly, pressure testing, and final commissioning. The project site is the Homestead Energy Services Power Plant (675 N. Flagler Ave, Homestead, FL). A non‑mandatory pre‑bid site visit is scheduled for September 2, 2026, and questions must be submitted by September 3, 2026. Final quotes are due September 8, 2026, with contract performance required to be completed within 60 calendar days of award. The City will evaluate proposals on price, qualifications, experience, schedule, and ability to meet warranty requirements.
• Scope: Full rebuild of blower and vertical drive (disassembly, inspection, machining, parts replacement, reassembly, testing).
• Location: Homestead Energy Services Power Plant, Homestead, FL.
• Timeline: Site visit 9/2/2026 (optional); Q&A 9/3/2026; Quote due 9/8/2026; Completion within 60 days of PO.
• Mandatory requirements: Valid Florida occupational/business license, appropriate insurance, E‑Verify enrollment, indemnity form for site visit.
• Evaluation factors: Experience with Fairbanks‑Morse equipment, licensing, ability to meet schedule, warranty provisions.
• Payment: Fixed‑price lump‑sum plus hourly rates for non‑scope labor; invoices payable within 30‑45 days of receipt.