The contract is for exterior and interior repairs on the Coates Building at Eastern Kentucky University. The work includes furnishing all labor, materials, equipment, and services necessary to complete the project. The contract has a substantial completion date of 240 calendar days after the start date and a final completion date of 270 calendar days after the start date. The contract also includes liquidated damages of $500 per day until substantial completion and $200 per day until final completion. Some key points about the project include:
• The project involves repairs to the Coates Building, including exterior and interior work.
• The contract has a substantial completion date of 240 calendar days after the start date.
• The contract has a final completion date of 270 calendar days after the start date.
• Liquidated damages are $500 per day until substantial completion and $200 per day until final completion.
• Bid bonds and performance bonds are required unless otherwise stated.