The contract is for the plugging of two wells, Govt 19-2 and Govt 29-1E, with associated reclamation of locations and access roads. The contract was awarded to Continental Industries, with costs for plugging the wells and reclamation. The contract also includes equipment hourly rates and third-party services.
• The cost to plug Govt 19-2 is $48,500.00/$53,500.00, with reclamation of location and access roads at $10,000.00.
• The cost to plug Govt 29-1E is $48,500.00/$53,500.00, with reclamation of location and access road at $10,000.00.
• Equipment hourly rates include rig, cement mixing and pumping, vac truck, back hoe, oilfield truck and trailer, and welder and acetylene torch.
• Third-party services have a re-bill charge of 20%.