The contract is for the renovation of the 4281 Departmental Storage Unit C at New Mexico State University. The project includes the removal and replacement of roofing, overhead doors, and expansion joints. The contract was awarded through an invitation to bid process, and the bid tabulations section lists several companies that submitted bids. The contract is expected to be completed within 90 calendar days after the notice to proceed. The contractor is required to provide a 5% bid bond and to comply with various laws and regulations, including the New Mexico Public Works Apprenticeship and Training Act and the New Mexico Workers' Compensation Act.
• The contract includes a base bid and several alternates, including the removal and replacement of roofing, overhead doors, and expansion joints.
• The contractor is required to provide a performance and payment bond if the subcontractor's work exceeds $125,000.
• The contract includes a liquidated damages clause, which provides for damages of $500 per day for late completion.
• The contractor is required to comply with various laws and regulations, including the New Mexico Public Works Apprenticeship and Training Act and the New Mexico Workers' Compensation Act.
• The contract includes a requirement for the contractor to provide a subcontractor listing, which includes the name and location of each subcontractor, the nature of the work to be performed, and the type and classification of license.