The Tyee Middle School Safety Project involves the removal of existing pavement, curb, sidewalk, and planter areas, as well as the construction of a mini roundabout, cement concrete curb and gutter, cement concrete sidewalk, and decorative concrete pavement entry treatments. The project also includes the installation of storm drainage modifications, HMA grind and overlay, landscaping and irrigation, and new channelization and signage. The engineer's estimate for the total project cost is $749,239.00.
• Remove Existing Pavement, Curb, Sidewalk, and Planter Areas
• Remove Structures and Obstructions
• Construct Mini Roundabout
• Construct Cement Concrete Curb and Gutter
• Construct Cement Concrete Sidewalk
• Construct Cement Concrete Curb Ramps
• Construct Decorative Concrete Pavement Entry Treatments
• Install Storm Drainage Modifications
• Perform HMA Grind and Overlay
• Install Landscaping and Irrigation
• Install New Channelization and Signage
• Property Restoration and Miscellaneous Work