This contract is a five‑year blanket‑order solicitation issued by the City of Spokane for the supply of mechanical spare‑replacement parts for its existing refuse‑crane system at the Waste‑to‑Energy Facility. The city will issue individual purchase orders on an as‑needed basis; prices are firm for the first year and may be adjusted annually thereafter. The award was recommended to Wemco Inc., and the estimated total spend (including tax) is roughly $273 K.
• Scope: Mechanical components (bearings, gears, encoders, brake sets, wheels, seals, etc.) for the refuse‑crane fleet.
• Delivery: Lead‑times range from 2‑3 days to up to 120 days, with freight prepaid by the city.
• Financials: Estimated subtotal $249,995.05; tax 9.1 %; total $272,744.60.
• Contract term: Dec 1 2025 – Nov 30 2030; firm‑price year first 12 months, annual price‑review on each anniversary.