The contract is for the West Bath Road Landslide Repair project, which involves repairing a landslide located approximately 100 to 500 feet east of the intersection of North Revere Road. The project includes slope repair using reinforced embankment and a Sierra-scape Retaining Wall, as well as reconstruction of approximately 600 feet of West Bath Road. The contract has an engineer's estimate of $1,600,312.18. The project is expected to be completed by May 31, 2021.
• The project involves slope repair and road reconstruction
• The contract has an engineer's estimate of $1,600,312.18
• The project is expected to be completed by May 31, 2021
• The contract was awarded to multiple vendors, including S.E.T., Inc., Eclipse Co., LLC, Kenmore Construction Co., Inc., Chieftain Trucking & Excavating, The Great Lakes Construction Co., Lockhart Concrete Co, and The Ruhlin Co. - Sharon Center, OH, and Shelly & Sands, Inc.