The contract concerns the exterior painting of the gymnasium and adjacent locker‑room buildings at St. Johns River State College’s Palatka Campus, including surface preparation, protection of existing fixtures, and replacement/painting of deteriorated wood fascia. The solicitation was open to pre‑qualified contractors, with a bid deadline of 9 Jan 2026; the college intends to award the contract to Thomas May Construction based on the lowest base‑bid of $113,800 plus unit‑price rates for fascia replacement. Key points include:
• Scope: pressure‑wash, prep, paint all exterior surfaces (brick, stucco, metal) and replace rotten 2×10 or 2×12 wood fascia at the roof eave, painting downspouts only.
• Procurement: full and open competition, single‑award, stipulated‑sum base bid with unit‑price fascia items.
• Awarded Vendor: Thomas May Construction (base bid $113,800; fascia unit rates $43.75/lf for 2×10 and $45.75/lf for 2×12).
• Schedule: Pre‑bid meeting 11 Dec 2025, addenda through 8 Jan 2026, bid deadline 9 Jan 2026, award recommendation 21 Jan 2026.