The contract is for the installation of a digester gas flowmeter at the South Cross Bayou facility. The contract was awarded to TLC Diversified Inc for a total amount of $822,800. The contract duration is approximately 323 days, starting from May 25, 2022, and ending on April 14, 2023. The contract includes provisions for progress payments, change orders, and termination. The contractor is required to comply with all applicable laws and regulations, including those related to public records.
• The contract includes a provision for the contractor to insert clauses related to subcontractors, requiring them to comply with the same provisions.
• The contract has a provision for the county to designate a representative for the prosecution of the work and interpretation of plans and specifications.
• The contract includes a provision for the resolution of conflicts between the terms of the contract documents.
• The contract has a provision for the contractor to provide public records relating to the agreement.
• The contract includes a provision for the binding agreement upon the executors, administrators, heirs, successors, and assigns of the contractor.