This contract covers the removal (where required) and installation of a high‑performance epoxy flooring system for the Outagamie County Highway Department’s warm‑storage and service‑shop areas (approximately 43,000 sf and 20,000 sf respectively). The work must use Sika‑specified products (PurCem 31NA primer, PurCem 24NA resurfacer, Sikafloor 264 topcoat), include a one‑year materials and workmanship warranty, and be executed in two‑phase halves to allow continued facility use. The procurement was a sealed‑bid, full‑open competition with a base bid around $410 k, and the award was made to Epoxy Solutions. Key contract dates include a bid deadline of May 15 2024, a contract award anticipated by May 24 2024, and substantial completion required by October 11 2024, with liquidated damages of $100 per day for late completion.