The S135 Pumping Station and Force Main Repair Project involves the furnishing of all labor, materials, tools, and equipment for the repair work. The project includes force main repair work and pumping station repair work. The engineer's estimate for the project is $2,220,848.00. The contract was awarded to Preston Pipelines with an apparent low bid of $3,380,000.00.
• The project requires a Class A license.
• A mandatory pre-bid conference was held on June 14, 2016.
• The project involves the repair of the S135 pumping station and force main.
• The contract was managed by the County of Sacramento's Construction Management & Inspection division.
• The project's bidding process was conducted through the County of Sacramento's online bidding system.