The Alaska Energy Authority (AEA) issued RFP 22080 to upgrade the Manokotak village power system. The award went to Gray Stassel Engineering, Inc. for professional engineering services divided into two phases: a Conceptual Design Report (Phase 1) and a full Final Design (Phase 2). Phase 1 required a 35 % design package and delivery by September 30 2022; Phase 2 required complete construction‑ready plans by June 30 2023. The contract is state‑funded, may be renewed for additional phases, and allows several pricing mechanisms (FPPE, FFP, CPFF). The solicitation emphasized Alaska‑business preference, DBE goals, and strict insurance and licensing requirements.
• Scope: feasibility studies, load analysis, equipment sizing, permitting, detailed civil‑mechanical‑electrical design, construction observation, O&M manuals, and optional bid/construction administration phases.
• Timeline: proposal deadline May 19 2022 → contract issuance May 30 2022 → Phase 1 CDR August 30–September 30 2022 → Phase 2 final design April 1–June 30 2023.
• Key Requirements: Alaska Business License, professional registration, $300 k CGL, $500 k E&O, and possible renewal for future work.