The contract is for emergency repairs to the Navarre Beach Causeway. The project involves repairing sections of the seawall and includes the purchase of materials such as dune sand, FRP material, and stainless-steel rods. The contract was awarded to Loftis Marine, LLC. with a total agreement amount of $1,840,049.50. The project is managed by the Santa Rosa County Engineering department. Key points of the contract include:
• The original agreement amount was $1,111,412.
• The addition of $728,637.50 was made due to changes in the project.
• The new completion date is July 1, 2025.
• The contract includes a change order that modifies the original agreement.