This contract involves a short‑duration civil construction effort at the Rock River Water Reclamation District’s treatment plant. The scope includes removal and replacement of a 6‑inch Portland‑cement‑concrete sidewalk around the chlorine contact tank, construction of a 6‑inch PCC paved ditch for plant drainage, installation of a utility trench with a PVC pipe and concrete headwall, and associated site‑preparation work (clearing, topsoil placement, seeding, and erosion‑control). The winning contractor, Stenstrom Excavation and Blacktop Group, is responsible for all labor, materials, and sub‑contracted services, and must comply with IDOT specifications, EPA erosion‑control standards, and a strict completion deadline of May 31 2019, with liquidated damages of $300 per day for any delay.
• Concrete sidewalk & ditch installation (≈ 1,120 sf total)
• Utility trench & concrete headwall installation (≈ 134 lf of trench)
• Site grading, topsoil placement, and seeding (≈ 300 sy)
• Tight schedule (≈ 2½ months) and stringent regulatory compliance requirements.