The contract involves implementing structural improvements and adding new communication equipment to the existing 80-foot-high communication tower. The project includes reinforcement and expansion of the existing concrete foundation and grade beam, added grounding/bonding, removal and replacement of the existing fence, placement of erosion control measures, and restoration of disturbed areas upon completion of the improvements. The engineer's estimate for the project is $135,000. The contract was awarded through a formal bid process, and the bid results list three bidders. The final award tabulation document is available for download, which may contain the actual award information.
• The project involves structural improvements to the existing communication tower.
• The project includes adding new communication equipment to the tower.
• The engineer's estimate for the project is $135,000.
• The contract was awarded through a formal bid process.
• The final award tabulation document is available for download.