The Sewer Standpipe Replacement project involves replacing 14 existing sewer standpipes with standard 4 ft. diameter precast concrete sewer manholes and two additional new sewer manholes, totaling 16 manholes. The project also includes providing sewage bypass pumping to accommodate a peak measured flow for 6” sewer main approximately 20 GPM for distances as required for each activity. The City of Keene's Public Works department initiated the procurement process for this project, but no responsive bids were received, and the project is being rebid for construction in 2024. Key aspects of the project include:
• Replacement of 14 existing sewer standpipes with precast concrete sewer manholes
• Installation of two additional new sewer manholes
• Provision of sewage bypass pumping
• Peak measured flow for 6” sewer main approximately 20 GPM
• Project rebid for construction in 2024