The Maggie Daley Field House Renovation project involves the renovation of the Daley Bicentennial Field House, with a total contract amount of $3,627,800. The project requires a minimum MBE/WBE participation of 28% MBE and 5% WBE. The work is to be substantially completed by October 15, 2014. Key aspects of the project include:
• Renovation of the field house
• Minimum MBE/WBE participation requirements
• Substantial completion by October 15, 2014
• Project schedule and milestone dates to be submitted by the contractor
• Pre-construction meeting scheduled for March 4, 2014