The contract is for the temporary relocation of family court rooms at One Montgomery Plaza. The work includes interior renovations of the 9th and 10th floors, with the goal of adding temporary courtrooms. The project must be completed while allowing for continuous occupancy of the building, and the contractor must work alongside the existing multi-phased replacement of the vertical facade and repairs to the roof. The contract also includes the management and coordination of construction and move activities, with the intent to minimize disturbance to building occupants. Some key points to consider are:
• The project requires interior renovations of approximately 23,900 SF.
• The contractor must work alongside the existing multi-phased replacement of the vertical facade and repairs to the roof.
• The project must be completed while allowing for continuous occupancy of the building.
• The contractor must minimize disturbance to building occupants.
• The contract includes the management and coordination of construction and move activities.