The contract is for the fabrication and installation of new horizontal storage tanks, including the removal of existing fencing and roof coverings, and the relocation of existing air compressor and refrigeration equipment. The project was solicited by VIA Metropolitan Transit, and the bid was rejected for CGC General Contractors, Inc. The project includes the installation of one 3,180 gallon super industrial cleaner storage tank and two 4,450 gallon new oil storage tanks.
• The project has a DBE utilization goal of 0%.
• The bid submission date was October 22, 2012, and the bid opening date was also October 22, 2012.
• A pre-bid conference was held on September 27, 2012.
• The contract documents include the IFB, abstract of minutes, and addenda.