The contract is for an elevator renovation project at Eastern Kentucky University's Richmond Campus. The work includes furnishing all labor, materials, equipment, and services necessary to complete the project. The contract was awarded to DC Elevator Company and Murphy Elevator, with bid prices of $214,500.00 and $207,920.00, respectively. The project has a substantial completion date of ninety (90) calendar days after the start date and a final completion date of one hundred twenty (120) calendar days after the start date. Key aspects of the project include:
• Elevator upgrades in the Commonwealth building
• Furnishing all labor, materials, equipment, and services necessary to complete the project
• Substantial completion date of ninety (90) calendar days after the start date
• Final completion date of one hundred twenty (120) calendar days after the start date
• Liquidated damages of $200 per day until substantial completion and $100 per day until final completion