The contract is for the Bear Parking Lot Green Infrastructure Improvements project at Brookside Reservation. The project involves the installation of green infrastructure components, including vegetated islands and bioswales, to reduce stormwater runoff and improve water quality. The contract was awarded to Chieftan Trucking & Excavation, Inc. for a lump sum bid of $183,500. The project is expected to provide storage of stormwater with controlled discharge for rain events and will also include asphalt paving, striping, and casting adjustments.
• The project is funded by a $137,500 grant from the National Fish and Wildlife Foundation.
• The contract includes the installation of green infrastructure components, including vegetated islands and bioswales.
• The project is expected to reduce stormwater runoff and improve water quality.
• The contract was awarded to Chieftan Trucking & Excavation, Inc. for a lump sum bid of $183,500.
• The project is expected to be completed under the terms of the contract, with the difference in cost and all related costs to be assumed by the original bidder and/or surety.