This contract procures new single‑phase pad‑mount transformers for the City of Dothan’s electric distribution system. The scope includes the supply and delivery of ten 75 kVA and nine 167 kVA transformers, each rated for a primary voltage of 7.62 kV and secondary voltages of 120 V/240 V (or 277 V). The winning bid, awarded to Gresco Utility, totals $204,504 and specifies a lead‑time of 20‑26 weeks for delivery. The procurement was conducted under open competition, with multiple vendors submitting bids that were evaluated on cost and required technical loss data.
• 10 units of 75 kVA pad‑mount transformers – $105,900 total
• 9 units of 167 kVA pad‑mount transformers – $98,604 total
• Awarded to Gresco Utility (Dothan, AL) as the lowest evaluated cost vendor
• Full bid opening on June 4 2024, award memorandum issued June 10 2024, final award June 18 2024