The City of McAllen is seeking a vendor to provide single machine repaving services for approximately 300,000 square yards of streets. The project includes milling, recycling, and overlaying of asphalt, as well as adjusting manholes and water valves to grade. The contract is expected to be completed within 100 working days. The awarded vendor, Cutler Repaving, Inc., has bid a total amount of $3,281,192.60, including alternates.
• The project includes recycling of existing asphalt and laying a new layer of asphalt.
• The contract includes adjusting manholes and water valves to grade.
• The vendor is required to complete the project within 100 working days.
• The contract includes a bid bond and payment and performance bonds.
• The City of McAllen reserves the right to reject any or all bids and to waive any or all formalities or technicalities.