This contract is for the extension of Mound Road from Greenhouse Road along Spring Drive to Cypress Drive – Segment 2 for Harris County Precinct 3. The project involves the construction of a new roadway section, including pavement, drainage, and detention pond. The contract was awarded to DVL Enterprises, LLC, with a total price of $2,541,190. The project is expected to provide a new road section to accommodate traffic and ensure reliable and safe transportation to businesses and residents of the area. Key aspects of the contract include:
• Construction of a 41-foot-wide concrete pavement section
• Transition to a 24-foot-wide asphalt pavement section
• Pavement ending in a cul-de-sac
• Existing railroad crossing at Cypress Drive to be closed
• Drainage to be a combination of swales and subsurface drainage
• Detention pond to be constructed
• Outfall to be constructed at Cypress Creek
The contract has a duration of 365 days, starting from December 10, 2024, and ending on December 9, 2025.