The contract is for the construction of a 4-inch diameter groundwater monitoring well, identified as Monitoring Well 39C, at the Kiefer Landfill. The work includes furnishing materials, drilling, and well development. The contract was awarded to multiple vendors, with ABC Liovin Drilling being the apparent low bid. The scope of work includes checking the site for subsurface utilities, reviewing and signing permit documents, and drilling using air rotary casing hammer.
• The contract requires a Contractor License C-57.
• The Engineer's Estimate for the project is $90,000.00.
• The contract documents, including project plans and specifications, are available on the County of Sacramento's website.
• A mandatory pre-bid conference was held on April 5, 2017, to review the site and answer questions.
• The bid opening was held on April 13, 2017, and the contract was awarded to the lowest bidder.