The contract is for the renovation of the Maintenance Barn at Harrison Hills Park, which includes the removal and disposal of the existing Homosote siding, the installation of a vapor barrier and horizontal wood furring strips, and the acceptance of the vertical board and batten vinyl siding. The contract also includes a contingency of 5% of the base bid. The contractor is required to commence the work within seven days after the issuance of the Notice to Proceed and to attain completion of the work within 90 days after the issuance of the Notice to Proceed. The contract value is $103,320.00.
Some key points of this contract include:
• The contract is for a fixed price of $103,320.00.
• The contractor is required to provide a performance bond and a payment bond.
• The contract includes a contingency of 5% of the base bid.
• The contractor is required to commence the work within seven days after the issuance of the Notice to Proceed and to attain completion of the work within 90 days after the issuance of the Notice to Proceed.
• The contract value is $103,320.00.