The contract involves the upgrade of doors and ADA access at the Mid Co East Dental Clinic. The project includes the phased demolition of existing doors and replacement with new ALUM storefront doors that meet wider ADA standards. The main entry door will also include the addition of an ADA button. The project requires coordination with county alarms trades for any keypad or security scope and includes small sprinkler scope and off-hour work requirements. The estimated start date is July 22, 2024, and the estimated final completion date is September 13, 2024.
• The project is part of a larger construction project and will be awarded on a lowest responsive bid basis.
• A mandatory walkthrough was held on June 4, 2024, and attendance at both the pre-proposal conference and walkthrough are required for proposal eligibility.
• The contract requires payment and performance bonds, and prevailing wage rates apply.
• The contract documents, including the project manual and drawings, are available for view and download on the Buyer Attachments page of the sourcing event.