The contract is for the upgrade of the elevator in the Campbell Building at Eastern Kentucky University's Richmond, KY Campus. The work includes furnishing all labor, materials, equipment, and services necessary to complete the project. The contract has a substantial completion date of 120 days from the start date and a final completion date of 135 days from the start date. The contract also includes liquidated damages of $200 per day until substantial completion and $100 per day until final completion. The contract value is estimated to be around $400,000. The key points of this contract are:
• The contract is for the upgrade of the elevator in the Campbell Building.
• The work includes furnishing all labor, materials, equipment, and services necessary to complete the project.
• The contract has a substantial completion date of 120 days from the start date and a final completion date of 135 days from the start date.
• The contract includes liquidated damages of $200 per day until substantial completion and $100 per day until final completion.
• The contract value is estimated to be around $400,000.